Work began in La Cristina, to the west of the Ajijic delegation.
La Cristina bridge still obstructed by large rocks. Photo: Sofía Medeles.
Sofía Medeles (Ajijic).- The streams that until a few months ago were clogged are now in the process of being cleared, so they will be clean before the rainy season, said Maximiano Macías Arceo. the acting delegate of Ajijic.
He added that work is underway and advancing as fast as possible in the streams of the western zone of Ajijic. These are the most obstructed streams, due to the mudslides that occurred in October of last year.
«Our goal, and the order of president Alejandro Aguirre Curiel, is to finish the works before the rains arrive. Both Civil Protection and the municipal government agree that Ajijic is a priority, due to the condition of the streams. However, city personnel are also focused on streams throughout the municipality,» he said.
He commented that in the days that they have been cleaning the first stream in La Cristina, they aren’t dealing much with garbage, but rather with the debris from the mudslides that occurred in October, mainly large stones.
«We are close to finishing and cleaning up,» he added. These works are being carried out by hand because the heavy machinery that they use to clean the riverbeds and bridges cannot reach the clogged areas.
When the cleaning of the first bridge is finished, Macías Arceo shared that they will clean eight more riverbeds and their bridges, from east to west, during the next few weeks.
Macías Arceo added that he would take advantage of the suitable stones excavated during the cleanup to use them for the paving and patching works in the streets of Ajijic.